Educational Institutions - Projects

Kodava Education Society
Project
Coorg Institute of Technology, Ponnampet, South Kodagu
Architects
Alur Associates
Consultants
Nagraj
Value of the Project
40 lakhs
Project Brief
  • 3.5kms. HT over head line work
  • Erection of 250kVA sub-station
  • Supply and installation of panel board
  • Power sanction
Duration
2 months
Status of work
Completed

Indian Institute Of Management - Bangalore
Project
Management Training Center
Architects
Stain Doshi & Balla
Consultants
Sanelac Consultant
Value of the Project
25 Lakhs
Project Brief
  • Electrical work for 60 executive rooms
  • Erection of LT panel
Duration
24 months
Status of work
Completed

Union Bank Of India
Project
Staff Training College at Bannerghatta, Bangalore
Architects
Radhika Somanna Associates
Consultants
Entask Electricals
Value of the Project
10 Lakhs
Project Brief
  • Electrification of 40 executive rooms with audio system
Duration
4 months
Status of work
Completed

Coorg Institute of Dental Sciences
Project
Dental College, Virajpet, Coorg
Architects
-
Consultants
-
Value of the Project
10 Lakhs
Project Brief
  • Erection of HT sub-station of 100kVA
  • Extension of 11Kv line for about 1km.
Duration
2 months
Status of work
Completed

Indian Evangelical Mission
Project
Out Reach Institute, Baglur
Architects
-
Consultants
-
Value of the Project
3 Lakhs
Project Brief
  • Lighting/power wiring
  • 1km. of LT overhead line
Duration
2 months
Status of work
Completed

St. Joseph College
Project
St. Joseph College of Commerce, Bangalore
Architects
Venkataraman Associates
Consultants
Procon Engineers
Value of the Project
5 Lakhs
Project Brief
  • Lighting and power cabling for 12 class rooms, auditorium, library
  • Laying of LT cable
  • Installation & servicing of main panel
Duration
10 months
Status of work
Completed

J.S.S Mahavidya Peeta
Project
J.S.S. College, Jayanagar, Bangalore
Architects
-
Consultants
-
Value of the Project
5 Lakhs
Project Brief
  • Additional power sanction for computer lab
  • Main cable laying
Duration
1 month
Status of work
Completed