Hospitals & Health Centre - Projects

Banashankari Medical & Oncology Research Centre Ltd.
Project
HCG Towers, P. Kalinga Rao Road, Bangalore
Architects
Gayathri & Namith Associates
Consultants
LnP Consultants
Value of the Project
1.5 crores
Project Brief
  • Erection of 750kVA HT sub-station with internal electrification
  • Electrification for PET CT, Cyclotron
  • Data & voice networking
Duration
4 months
Status of work
Completed

Banashankari Medical & Oncology Research Centre Ltd.
Project
Cyber Knife, P. Kalinga Rao Road
Architects
Vinyas Architects
Consultants
LnP Consultants
Value of the Project
1.4 crores
Project Brief
  • Erection of 315kVA HT sub-station with internal electrification
  • Electrification for CYBER KNIFE & LINAC machines
  • Data & voice networking
Duration
9 months
Status of work
5% Completed

Health Care Global Enterprises Pvt. Ltd.
Project
Gokul Institute Of Oncology, Ramaiah Hospital, Bangalore
Architects
Gayathri & Namith Associates
Consultants
Servelec Consultants
Value of the Project
55 Lakhs
Project Brief
  • Electrification for LINAC machine
  • Data & voice networking
Duration
2 months
Status of work
Completed

Health Care Global Enterprises Pvt. Ltd.
Project
NMR Curie Centre, Hubli
Architects
-
Consultants
Tandem
Value of the Project
43 Lakhs
Project Brief
  • Electrification for LINAC machine
  • Data & voice networking
Duration
6 months
Status of work
30% completed

K. H. S. D. P
Project
Government Hospital, Polibetta, Coorg
Architects
Hoskere Shankar
Consultants
-
Value of the Project
40 Lakhs
Project Brief
  • Erection of 100kVA HT sub-station with internal electrification
  • Extension of 11kv line for about 1km.
Duration
2 months
Status of work
Completed

Health Care Global Enterprises Pvt. Ltd.
Project
Malnad Hospital, Shivamoga
Architects
-
Consultants
-
Value of the Project
35 Lakhs
Project Brief
  • Electrification for LINAC machine
  • Data & voice networking
Duration
2 months
Status of work
Completed

Vital Medi-Health Care Pvt. Ltd.
Project
Diagnostic Centre, Indiranagar, Bangalore
Architects
Sarab Designs
Consultants
Ceecon
Value of the Project
22 Lakhs
Project Brief
  • 160kVA sub-station & electrification of pneumatic machines
  • Internal electrification
Duration
-
Status of work
Completed