Layout Electrification - Projects

ETA Star Property Developers Ltd.
Project

Star Rodeo, Bidadi

Architects
JDS Architects
Consultants
Jurong Consultants (India) Pvt Ltd.
Value of the Project
4 crores
Project Brief
  • 2mVA sub-station yard with cabling
Duration
-
Status of work
10% completed

Nu-Tech Prasiddhi Consortium
Project

Cloud 9, Bommasandra

Architects
-
Consultants
-
Value of the Project
1.5 crores
Project Brief
  • 5kms. of HT under ground cable
  • 15kms. of LT under ground cable
  • Erection of 10 out door transformer yard
Duration
-
Status of work
Completed

Golden Gate Properties Pvt Ltd.
Project
  1. Harmony, Attibele
  2. Liberty Acres, Indlbele
  3. Woods, Sarjapur Road
Architects
-
Consultants
-
Value of the Project
2.5 crores
Project Brief
  • 3kms. of HT under ground cable
  • 10kms. of LT under ground cable
  • Erection of 7 out door transformer yard
Duration
Status of work
completed

M. J.Associates
Project
  1. Wellington Paradise
  2. Dream Paradise
Architects
-
Consultants
-
Value of the Project
1.1 crore
Project Brief
  • 3kms. of HT over head work
  • 10kms. of LT over head line work
  • Erection of 9 out door transformers
Duration
3 months each project
Status of work
Completed

Mr. Naik
Project
Naik Residency
Architects
-
Consultants
-
Value of the Project
45 lakhs
Project Brief
  • 1kms. of HT over head work
  • 5kms. of LT over head line work
  • Erection of 4 out door transformer yard
Duration
3 months
Status of work
Completed

Prasiddi Builders
Project
Prasiddi Park Dale, Hesaraghatta, Bangalore
Architects
Sumana M.
Consultants
S&SU Associates
Value of the Project
42 lakhs
Project Brief
  • 1kms. of HT over head work
  • 4v of LT over head line work
  • Erection of 5 out door transformer yard
Duration
-
Status of work
40% completed

KPTCL -Bangalore
Project
Electrification of Kumaraswamy Layout, Bangalore
Architects
-
Consultants
-
Value of the Project
24 lakhs
Project Brief
  • 1.5kms. of HT over head work
  • 4kms. of LT over head line work
  • Erection of 6 out door transformer yard
Duration
6 months
Status of work
Completed